SOS NERC Prep - Reliability Exam
The Reliability Coordinator just informed you of a slow time error correction which will begin at
the top of the next hour. Your EMS system will not let you change your scheduled freque
...
SOS NERC Prep - Reliability Exam
The Reliability Coordinator just informed you of a slow time error correction which will begin at
the top of the next hour. Your EMS system will not let you change your scheduled frequency.
Your Frequency Bias Setting is -100 MW/.1Hz. What action should you take?
A) Increase Net Interchange Schedule by 20 MWs.
B) Inform the Reliability Coordinator that you cannot participate in the time error correction.
C) Decrease Net Interchange Schedule by 20 MWs.
D) Increase Net Interchange Schedule by 10 MWs. - ✔✔A) Increase Net Interchange Schedule
by 20 MWs.
A Balancing Authority has a sudden loss of a large block of load in its area. This loss will be
seen instantaneously in the change of which of the following values?
1. Actual Net Interchange
2. Scheduled Frequency
3. Scheduled Net Interchange
4. Area Control Error
A) 4 only
B) 1 & 3
C) 1 & 4
D) 3 & 4 - ✔✔C) 1 & 4
Metered Data included in the calculation of ACE are: dynamic schedules, pseudo ties, actual
frequency, and all __________.
A) Tie lines readings
B) Generators output
C) Scheduled frequency indications
D) Transformer load - ✔✔A) Tie lines readings
Balancing Authority A is currently reading a system frequency of 60.00 Hz. Its Net Actual
Interchange is +100 MW and its Net Scheduled Interchange is +200 MW. If Balancing Authority
A's frequency bias setting is 100 MW/0.1 Hz, what is ACE?
A) -100
B) 0
C) 10
D) 100 - ✔✔A) -100
A Balancing Authority has a Net Interchange Schedule of -250 MWs from 1200 to 1600 on a
summer day. The Net Interchange Actual for those same hours respectively were -230 MW, -275
MW, -250 MW and -270 MW. What was the Balancing Authority's Inadvertent Interchange for
the 4-hour period?
A) 6 MWs out
B) 25 MWs in
C) 25 MWs out
D) 6 MWs in - ✔✔B) 25 MWs in
For the ACE equation to work properly, dynamic schedules, pseudo ties, frequency, and all
________________ must be metered.
A) Generation
B) Communications
C) Transformers
D) Tie lines - ✔✔D) Tie lines
If the frequency bias setting is set to a less negative value than the frequency response of a
Balancing Authority and a frequency increase is caused by a sudden loss of load in an external
balancing area, what will be the result?
A) The ACE will be zero and will take no AGC action
B) The ACE will be a negative value and AGC will increase generation
C) The ACE will be a positive value and AGC will lower generation
D)This will not affect the ACE - ✔✔B) The ACE will be a negative value and AGC will
increase generation
If the frequency bias setting is less negative than the frequency response of a Balancing
Authority and a frequency decline is caused by a sudden loss of generation in an external
balancing area, what will be the result?
A) The ACE will be a negative value and AGC will increase generation.
B) This will not affect the ACE.
C) The ACE will be a positive value and AGC will low
[Show More]