NERC Exam Study Guide Questions
Two phase conductors of a 138kV transmission line come in contact due to a storm, creating a
phase to phase fault. The distance relay at each end of the line tripped and isolated the lin
...
NERC Exam Study Guide Questions
Two phase conductors of a 138kV transmission line come in contact due to a storm, creating a
phase to phase fault. The distance relay at each end of the line tripped and isolated the line. What
two measured parameters of the line caused the distance relay to operate?
Temperature and length
MWs and MVARs
Voltage and current
Resistance and Impedance - ✔✔Voltage and current
What is the main cause for having low voltage on the Transmission and Distribution system?
Over generation in the Interconnection
Not enough transmission line in service
Excessive of reactive resources
A shortage of reactive resources - ✔✔A shortage of reactive resources
The largest single contingency for Balancing Authority A is a unit rated at 900 MW. Which of
the following disturbances would constitute a reportable disturbance for DCS evaluation based
on the NERC DCS criteria?
The loss of a 700 MW generating unit at 100% output.
The loss of the 900 MW generating unit at 60% output.
The loss of two 400 MW units 30 seconds apart.
The loss of 750 MW of firm load. - ✔✔The loss of two 400 MW units 30 seconds apart.
Which of the following actions is appropriate for preserving the reliability of the Interconnection
during a low voltage emergency?
Switch in reactors
Arrange for interchange sales during high price periods
Removing key transmission lines from service
Raise generator - ✔✔Raise generator
A conductor is rated for 180 MVA, the current transformer at one end is rated at 160 MVA and
the bus is rated at 200 MVA. What is the MVA limit for this transmission line?
180 MVA
200 MVA
160 MVA
100 MVA - ✔✔160 MVA
Frequency has been running at 59.96 Hz for the last hour and your ACE has hovered right at zero
for the entire hour. Your Frequency Bias Setting (B) is 50 MW/.1 Hz. What would be your
approximate Inadvertent Interchange for the hour?
Zero
40 MWs out
20 MW out
20 MWs in - ✔✔20 MW out
Which entity integrates resource plans ahead of time, maintains load-interchange-generation
balance within a Balancing Authority Area, and supports Interconnection frequency in real time?
Transmission Operator
Reliability Coordinator
Balancing Authority
Regional Reliability Organization - ✔✔Balancing Authority
Training staff must be identified, and competent in both knowledge of system operations and
_____________.
finance issues
planning
instructional capabilities
power marketing - ✔✔instructional capabilities
On a mild spring day, a transmission line trips. The line then trips again when energized. Which
of the following is least likely to be the problem?
Overload
Equipment failure
Sabotage
Vandalism - ✔✔Overload
When energy demand and operating reserves require all resources dedicated to firm load and
maintaining regulating reserves, what action(s) should be taken?
Issue NERC EEA1
Request local Balancing Authorities to start off-line generating resources.
Request generation output at maximum levels
All of the Above - ✔✔All of the Above
A Balancing Authority that is experiencing a potential capacity or energy emergency and
communicates its current and expected future system conditions to its Reliability Coordinator.
What would likely be the Reliability Coordinators first action?
Notify all Reliability Coordinators
Notify the deficient BA marketers
Notify other Balancing Authorities and Transmission Operators in its Reliability Coordinantor
Area
Order Load Shed - ✔✔Notify other Balancing Authorities and Transmission Operators in its
Reliability Coordinantor Area
A 500-MW generator trips in a Balancing Authority external to your Balancing Authority Area.
Which of the following responses would you expect to see in your Area?
Reduced net actual interchange.
Reduced net generation on your system.
Frequency above 60.00 Hz.
Net Actual Interchange would be greater than Scheduled Interchange - ✔✔Net Actual
Interchange would be greater than Scheduled Interchange
A Reliability Coordinator receives notification from a Balancing Authority within its Reliability
Coordinator area that the BA is experiencing a potential Energy Emergency. The RC shall
initiate the Energy Emergency Alert (EEA) process as detailed in Attachment 1-EOP-001,
Energy Emergency Alerts. What actions would the Reliability Coordinator coordinate with other
Reliability Coordinators that have available resources?
[Show More]